Aurora Road Infrastructure Project - Phase 1 Update 12/8/23

AuroraRdLocalDetourMap 12-18


12/8/23  The week of December 18th, the one-way eastbound zone on Aurora Road will be extended east past Liberty Road and Andre Lane. Northbound and Southbound traffic will be maintained on Liberty. Two-way local traffic will be maintained form the east of the construction zone to Pettibone Road.    Map


12/4/23  This week Tri Mor successfully passed a pressure test of the new 12” water main from the west end of the project to Liberty Road. The Cleveland Water Department has begun the process of chlorinating the new water main.


174f221c-a27e-e5bf-b056-23fb0a4c502c

Work Completed This Week

Tri Mor has completed extending sanitary sewer laterals and cleanouts to the right-of-way on the south side of Aurora Road from the west end of the project to Liberty Road.  The new water main from the west end of the project to Liberty  Road has passed.



66d9a92f-e162-411d-96e3-dd1b3ebd5bc52-Week Look Ahead

During the next two weeks Tri Mor crews will begin installing new water services from the new water main to the right-of-way a teach building from the west end of the project toward Liberty Road and connecting the buildings to the new water main. The process will require a brief (approximately ½ hour) shut down of water at each building as it is connected. Tri Mor will knock on the door of each building as the connection time approaches to verify a good time for the transition.



08c4e168-7ea8-6247-5e34-69b6a1a708c4

Leaf Collection in the Aurora Road Construction Zone will continue to occur every Sunday morning.



2e48b1a5-07ea-0c8f-6332-58a7e620b867The week of December 18th, the one-way eastbound zone on Aurora Road will be extended east past Liberty Road and Andre Lane. Northbound and Southbound traffic will be maintained on Liberty. Two-way local traffic will be maintained form the east of the construction zone to Pettibone Road.