Work Completed This Week

With one exception, Tri Mor has completed transferring water service connections to the new water main west of Liberty Road.   They have also completed extending sanitary lateral cleanouts to the right-of-way on the south side of Aurora Road west of Liberty.



26254bc7-9577-6425-c4a8-834068961f912-Week Look Ahead

Although no work was scheduled to be performed from December 25th through January 1st, crews will be on site Wednesday the 27th to coordinate trash collection and complete the final water service connection west of Liberty Road.

Beginning January 2nd, Tri Mor crews will saw cut the trench across Liberty Road and begin extending the new 12” water main across Liberty Road to the east end of the project.  They will connect the various side streets to the new water main on the west side of Liberty Rd and begin the installation of new storm sewers on the south side of Aurora Road west of Liberty Road.




Traffic Maintenance Change

On December 18th, the one-way eastbound zone on Aurora Road was extended east past Liberty Road and Andre Lane.  Northbound and Southbound traffic will be maintained on Liberty road.  Two-way local traffic will be maintained from the east end of the construction zone to Pettibone Rd.