Aurora Road Infrastructure Project - Phase 1 Update 1/12/24

93acef06-8c66-4924-d9d8-aa4b404510a8


93acef06-8c66-4924-d9d8-aa4b404510a8

Work Completed This Week

TriMor crews continued installing new 12” water main on the south side of Aurora Road west of Liberty Road.  They also installed short sections of storm sewer on the south side of Aurora Road from the west project limit to Portz Parkway.

2-Week Look Ahead

Although no work was scheduled to be performed from December 25th through January 1st, crews will be on site Wednesday the 27th to coordinate trash collection and complete the final water service connection west of Liberty Road.

Beginning January 2nd, Tri Mor crews will saw cut the trench across Liberty Road and begin extending the new 12” water main across Liberty Road to the east end of the project. They will connect the various side streets to the new water main on the west side of Liberty Rd and begin the installation of new storm sewers on the south side of Aurora Road west of Liberty Road.



Additional Information

Trash Collection Reminder: Be sure to place your trash and recycle cans out before 7:00 am every Wednesday.

Mail Delivery: It is recommended that all residents pick up their mail daily.

Project Communication: As a result of discussions during the Project Resident Meeting, various project correspondences are sent directly to resident’s email site.  If you are not receiving these weekly and special notifications and would like to be included on our list please send your email address to mrizzo@solonohio.org so we can add you to our Aurora Road Reconstruction Contact List.